Condo Public Facility Handover and Inspection Guide
🇹🇼 Looking for the Chinese version of this article?切換至繁體中文版 →

Condo Public Facility Handover and Inspection Guide

This article is general information for reference only and is not legal, tax, medical or engineering advice. Rules, fees and subsidies change; check the latest notice from the responsible authority before acting. For electrical, gas, structural or health risks, consult a licensed professional.

This is the English edition of a Chinese article, adapted with AI assistance and checked against the original. Where the two differ, the Chinese version and the official sources it cites prevail.

When newly formed condominium management committees conduct public facility handovers, developers (constructors) must inspect plumbing, electrical, mechanical, fire protection, and utility lines jointly with the committee under Article 57 of the Condominium Administration Act (公寓大廈管理條例), transferring complete blueprints and public reserve funds within 7 days of verified functional testing. If inspections uncover defects or divergence from approved completion drawings, developers bear full statutory responsibility for repair costs; until deficiencies are rectified, management committees must never prematurely execute handover acceptance agreements.

Important Notice: Private unit inspections involve individual owners inspecting private apartment interiors (flooring, window frames, outlets, drainage), whereas common area handovers involve management committees representing all co-owners to inspect building-wide emergency generators, fire booster pumps, elevators, sewage sumps, rooftop waterproofing, and basement parking ramps. Because legal bases and engineering scopes differ, most committees retain third-party professional MEP building inspection firms to assist with technical testing.

Condominium Act Article 57: Inspection Procedures and Fines

First-term condominium committees often remain unaware of their statutory bargaining leverage. Articles 57 and 49 of the Condominium Administration Act impose strict legal handover mandates on developers:

Statutory ItemRegulatory Provision (Condominium Administration Act)Management Committee Practical Oversight
Transfer Deadline and InventoryArticle 57, Paragraph 1: Constructor must inventory common elements, agreed common areas, and auxiliary equipment, transferring them jointly within 7 days after committee formation or manager appointment.Demand complete equipment catalogs, completion drawings, MEP/fire schematics, and original use permits before scheduling on-site testing.
Four Major Systems Joint TestingArticle 57, Paragraph 2: On-site functional testing across plumbing, electrical, mechanical, fire safety, and utility lines must confirm proper operation before handover proceeds.Never rely on visual checks; actively run emergency diesel generators, fire booster pumps, smoke extraction fans, and sump pumps.
Defect Rectification ResponsibilityArticle 57, Paragraph 3: Constructors must repair defects or non-compliant items at their sole expense; local authorities may dispatch officials upon application.Compile initial inspection defect lists with deadlines; sign handover only after re-inspection passes; request municipal building bureau witnessing if needed.
Public Reserve Fund DisbursementArticles 18 and 57: Mandatory public funds deposited by constructors based on construction cost ratios are disbursed from municipal custody into committee accounts after handover.Developers often urge signing handovers to release funds; committees must stand firm until major MEP and fire protection defects are resolved.
Developer Refusal PenaltyArticle 49, Paragraph 1, Item 8: Constructors violating Article 57 face administrative fines between NT$40,000 and NT$200,000 (4 萬元以上 20 萬元以下) from municipal authorities, imposed consecutively per violation.If constructors delay submitting as-built plans or refuse repairs, send legal attest letters and report violations to municipal building inspection authorities.

To audit private apartment interiors, utilize our home inspection checklist tool for outlet and plumbing checks; statutory rules on condominium fee enforcement are detailed in condominium management fee arrears legal guides.

Five Core Systems in Handover Inspections (MEP, Fire, Water, Civil)

In practice, the most expensive latent building defects lie concealed in plant rooms, pipe shafts, and basements. Joint testing with certified engineers must audit five primary areas:

Core System CategoryCritical On-Site Inspection Points and Functional TestsCommon Hidden Defects and Contractor Cutting Corners
1. Electrical and Generator SystemsSimulate utility power cuts to verify Automatic Transfer Switches (ATS) start diesel generators within 10 to 30 seconds; test emergency lighting and phase sequence correctness.Substandard cable cross-sections; unlabeled distribution panels; generator fuel tanks lacking required reserve diesel; defective battery chargers.
2. Fire Protection and Smoke ControlTrigger smoke detectors to verify fire alarm panels link with stairway pressurization fans and elevator recall; test hose nozzle terminal water pressure (above 1.7 kg/cm²).Fire damper blades jammed; inadequate terminal nozzle pressure; missing fire hose nozzles; expired extinguisher inspection tags; inoperable rooftop smoke hatches.
3. Water Supply, Drainage, and WastewaterTest automatic alternating cycles for dual booster pumps; inspect rooftop overflow alarms; test float switches and dual submersible pumps in sewage/drainage sumps.Reversed check valves; construction debris blocking sewage sumps; missing high-water alarm sirens; absence of air-gap backflow preventers.
4. Civil Construction, Roofing, and ParkingConduct 48-hour flood tests on rooftop waterproofing; test basement ramp non-slip grooving and electric rolling shutter obstacle rebound safety sensors.Ponding water on flat roofs; expansion joint caulking fissures; inadequate concrete cover causing basement ceiling rust spots; inoperable shutter safety edges.
5. Blueprint and Permit ReconciliationCross-check as-built architectural drawings, structural sheets, and fire layouts against physical installations room-by-room; verify electrical single-line diagrams.Illegal secondary construction altering open space allocations; discrepancies between drawing ratings and installed motor horsepowers; unapproved equipment substitutions.

Verify building licensing dates using our use permit age lookup guide.

Essential Documents and Drawings in Handover Inventories

Committees must ensure developers deliver all original documentation and operating manuals:

  • Original Use Permit (使用執照正本) and approved completion drawings (full architectural, structural, MEP, fire protection, and HVAC blueprints alongside CAD electronic files).
  • Elevator and Pressure Vessel Safety Certificates, maintenance contracts, factory test reports, and warranty certificates.
  • Fire Equipment Approval Certificates, fire inspection completion clearance forms, and test performance logs.
  • Water Tank Cleaning and Disinfection Reports, initial water quality laboratory test certificates, and sewer connection approvals.
  • Equipment Operation Manuals, manufacturer warranties, vendor maintenance directories, and master keys for plant rooms and rooftop accesses.

Frequently Asked Questions

Is Developer Claim That Funds Require Signing Handovers True?

No. Public reserve funds are held in municipal escrow under Article 18. Municipal agencies disburse funds once statutory joint functional testing completes; developers cannot withhold funds to force waivers on major safety defects.

Are Re-Inspections Limited to a Single Round If Deficiencies Persist?

No. Article 57, Paragraph 3 stipulates that developers must repair defects at their own expense until functions operate properly. Committees can schedule multiple re-inspections until all deficiencies pass.

How Much Do Third-Party Inspection Firms Cost and Who Pays?

Costs typically range from NT$80,000 to NT$250,000 (8 萬至 25 萬元; up to NT$300,000) depending on building height and unit counts. Committees fund inspections from initial management fee surpluses or constructor cooperation budgets.

Is the Developer Liable If Rooftop Leaks Occur Post-Handover?

Yes. Civil Code Article 365 defect liability and contract structural warranties (typically 1 to 5 years for waterproofing and 15 years for structural components) continue to bind developers after handover.

Last updated: 2026-11-01.