In major metropolitan areas 在台灣各大都會區, walk-up older apartments with a building age 屋齡 of 30 years to 50 years or more account for a very high proportion 佔比極高. As the first generation of owners enters old age as senior citizens 高齡銀髮族, many seniors face steep and narrow stairs due to joint degeneration, strokes, or mobility issues, sometimes even becoming "homebound elderly" 困居老人 who cannot leave home year-round. In recent years, various county and city governments have launched high elevator addition subsidy plans reaching 高達 200 萬至 300 萬以上的高額增設電梯補助方案 to promote barrier-free friendly environments 無障礙友善環境. However, adding elevators to old apartments involves the consent rights of all residents, statutory open space area, structural seismic safety, and subsequent maintenance fee sharing 全體住戶同意權益, 法定空地面積, 建築耐震結構安全與後續電梯維護費用分攤, and poor planning often leads to failure 功敗垂成.
Old Apartment Elevator Subsidy and Structural Guide

This article is compiled from publicly available online sources for general reference only; readers should independently verify and judge its accuracy, and it is not legal, tax, medical or engineering advice. Rules, fees and subsidies change; check the latest notice from the responsible authority before acting. For electrical, gas, structural or health risks, consult a qualified professional.
This is the English edition of a Chinese article, adapted with AI assistance and checked against the original. Where the two differ, the Chinese version and the official sources it cites prevail.
Regulations and Subsidy Highlights: According to the "Barrier-Free Residential Improvement Project" 無障礙住宅改善工程 promoted by the National Land Management Agency 國土管理署 of the Ministry of the Interior 內政部 and the elevator addition subsidy guidelines 電梯增設補助要點 of the Taipei and New Taipei 雙北市政府都市更新處 Urban Renewal Division, eligible older apartments adding barrier-free elevators 無障礙電梯 can receive high government subsidies of 45% to 50% of the total engineering cost and an upper limit of 2 萬至 3 萬元以上之高額政府補助! In addition, the Building Technical Regulations 建築技術規則 has relaxed building coverage and floor area ratio limits for adding elevators to old buildings 老屋增設電梯之建蔽率與容積率限制, significantly lowering urban planning regulatory thresholds 都市計畫法規門檻.
1. Two Core Paths for Adding Elevators to Old Apartments: Outdoor Statutory Open Space vs. Stairwell Atrium
Adding elevators to old buildings is not feasible for every building and requires sufficient physical space conditions 老屋加裝電梯並非每棟都能裝, 必須具備足夠的物理空間條件:
- Form A: Outdoor Statutory Open Space Independent Lobby Addition (Most Mainstream) 形式 A: 戶外法定空地獨立梯廳增設 (最主流) : Utilize the statutory open space (garden or open space) 法定空地 (花園或空地) in front, back, or side of the apartment to build a new foundation, erecting a steel-framed (SC/SS) 鋼骨結構 glass curtain wall elevator tower, and then connecting through the exterior wall to the original stair landing or balconies of each household via a steel-framed walkway 鋼構走道. This construction method has the least impact on the original indoor living structure with good lighting and ventilation 採光通風良好.
- Form B: Utilization of Existing Spiral Staircase Central Atrium Addition (Extremely Narrow Micro Elevator) 形式 B: 利用既有旋轉樓梯中央天井增設 (極窄微型電梯) : In the past, some four- and five-story old apartments reserved a wider atrium (hollow light-transmitting area) 天井 (中空透光區) in the center of the stairs. If the net size of the atrium is 1.2 meters × 1.2 meters or more 1.2 米 × 1.2 米以上, a machine-room-less 無機房型 steel-cable micro barrier-free elevator can be evaluated. However, this method requires cutting the existing stair handrails 既有樓梯扶手進行削切, and the construction space is extremely narrow 極其狹窄.
2. Resident Intention Integration: Statutory Consent Ratio Threshold and Funding Allocation Golden Formula
The biggest obstacle to adding an elevator is often not technology, but human communication 加裝電梯最大的阻礙往往不是技術, 而是"人的溝通":
- Latest Regulatory Consent Ratio Threshold 最新法規同意比例門檻: Previously, according to the Condominium Administration Act 公寓大廈管理條例, 100% consent of all owners was required, leading to first-floor residents often exercising veto power 一票否決. The Ministry of the Interior 內政部 has revised and relaxed this: applying for an elevator addition construction license requires the consent ratio threshold to be reduced to three-quarters (75%) or more attending and a majority consenting 申請"增設電梯建造執照", 同意比例門檻降為"四分之三 (75%) 以上出席並過半數同意"; if taking the urban renewal reconstruction and maintenance procedure, the threshold is also greatly relaxed. However, in practice, because the project occupies the first-floor open space or excavates underground piping and wiring 管線, obtaining the understanding and signature of the first-floor residents makes project promotion smoothest.
- Floor Funding Ratio Allocation Standard (Recommended Market Fair Formula) 樓層出資比例分攤標準 (推薦市場公平公式) :
- First-Floor Residents 一樓住戶: Does not use the elevator at all and sacrifices some front-door open space, with a funding ratio of 0% 出資比例為 0%, and the community can even promise to exempt them from future public electricity and maintenance fees for the elevator or provide moderate parking space compensation 社區甚至可承諾免除其未來電梯之公共電費與保養費, 或提供適度停車空間補償.
- Second-Floor Residents 二樓住戶: Contributes about 5% to 10% 出資約 5% 至 10%.
- Third-Floor Residents 三樓住戶: Contributes about 15% to 20% 出資約 15% 至 20%.
- Fourth-Floor Residents 四樓住戶: Contributes about 30% to 35% 出資約 30% 至 35%.
- Fifth-Floor Residents 五樓住戶: Benefits the most and suffers the most from climbing stairs, contributing about 40% to 45% 受惠最大, 爬樓梯最苦, 出資約 40% 至 45%.
3. Building Structural Safety Seismic Evaluation and Four Steps to Apply for Construction Licenses
After decades of earthquake weathering, can an old apartment bear an elevator tower weighing several metric tons? It must be entrusted to professional structural engineers for rigorous review 老公寓在經歷數十年地震風化後, 是否能承受一座重達數公噸的電梯塔?必須委託專業結構技師層層把關:
Step 1: Entrust an Architect for On-Site Feasibility Evaluation (Preliminary Survey) 第一步: 委託建築師進行現場可行性評估 (初勘) :
Review the original use license completion drawings of the building, and measure whether the statutory open space size, air defense basement location, and fire lane net width comply with the fire safety regulations requiring a fire evacuation passage of 1.5 meters or more 調閱建物原始使用執照竣工圖, 丈量法定空地尺寸, 防空地下室位置, 防火巷淨寬度是否符合消防法規要求的 1.5 米以上防火避難通道.
Step 2: Structural Seismic Safety Preliminary Evaluation and Geological Drilling 第二步: 結構耐震安全初評與地質鑽探:
The added elevator tower has independent foundation load-bearing piles, and it must be confirmed whether pile driving and excavation will destroy the soil layer stability of the original old apartment's shallow foundation, and whether existing main structural walls need local seismic reinforcement 增設電梯塔具有獨立的基礎承重樁, 必須確認打樁開挖是否會破壞原老公寓淺基礎之土層穩定; 既有主結構牆體是否需做局部耐震補強.
Step 3: Apply for Construction Licenses from County and City Bureau of Public Works 第三步: 申請各縣市工務局建造執照:
Detailed engineering drawings are drawn by a licensed architect and submitted to the competent authority to review fire evacuation circulation and sunshine shadow analysis, obtaining the formal construction license for adding elevating equipment 由開業建築師繪製詳細工程圖說, 送主管機關審查防火避難動線, 日照陰影分析, 取得正式"增設昇降設備建造執照".
Step 4: Apply to Urban Renewal Division / Bureau of Public Works for Government Million-Dollar Subsidies and Award Contracts for Construction 第四步: 向都更處/工務局申請政府百萬補助款並發包動工:
After obtaining the construction license, formally submit the subsidy application. Once approved, qualified elevator lifting equipment professional construction contractors enter the site for construction. After completion and passing the Bureau of Standards, Metrology and Inspection test run, the use license is issued and the subsidy is disbursed 取得建照後正式送交補助申請, 審查通過後由合格電梯升降設備專業營造廠進場施工, 完工通過標準檢驗局試車後核發使用執照並撥付補助款.
4. Comparison of Various Construction Methods and Base Condition Evaluations for Adding Elevators to Old Buildings
| Elevator Addition Construction Method 增設電梯工法 | Minimum Base Size Required 所需最小基地尺寸 | Impact on Existing Old Building Structure 對既有老屋結構影響 | Estimated Total Cost (Excluding Subsidies) 預估總造價 (未扣補助) | Estimated Construction Period 施工工期預估 |
|---|---|---|---|---|
| Outdoor Independent Steel Frame Elevator Tower 戶外獨立鋼骨電梯塔 | Open space length and width about 2.2m × 2.0m 空地長寬約需 2.2m × 2.0m | Very low (independent steel columns and pile foundations bear weight) 極低 (獨立鋼柱與基樁承載) | About 4,500,000 to 6,000,000 NTD 約 450萬~600 萬元 | About 6 to 8 months 約 6~8 個月 |
| Staircase Atrium Micro Elevator 樓梯天井微型電梯 | Atrium length and width 1.3m × 1.3m or more 天井長寬需 1.3m × 1.3m 以上 | Medium (need to cut part of the stair surface and rebar planting) 中等 (需削切部分梯面並植筋) | About 3,500,000 to 4,500,000 NTD 約 350萬~450 萬元 | About 4 to 6 months 約 4~6 個月 |
| Stairwell Exterior Balcony Switching Elevator 樓梯間外側陽台切換梯 | Requires a spacious back alley outside the rear balcony 需後陽台外側有寬敞後巷 | Medium (balcony needs door openings knocked out) 中等 (陽台需敲打門洞做開口) | About 4,000,000 to 5,000,000 NTD 約 400萬~500 萬元 | About 6 to 7 months 約 6~7 個月 |
| Stair Climber / Stair Lift (Backup) 樓梯爬梯機/升降椅 (備案) | Stair net width 80cm or more is sufficient 樓梯淨寬需 80cm 以上即可 | Zero damage (tracks locked directly to stairs) 零破壞 (直接軌道鎖於樓梯) | About 400,000 to 800,000 NTD (per household) 約 40萬~80 萬元 (每戶) | About 2 to 3 days to complete 約 2~3 天完工 |
5. Official Building Elevating Equipment Specifications and Subsidy Regulations
For seismic design and barrier-free dimensions of added elevating equipment 增設昇降設備耐震設計與無障礙尺寸規範, follow Article 167-6 of the Building Technical Regulations Construction Edition 《建築技術規則建築設計施工編》第 167 條之 6 promoted by the National Land Management Agency 國土管理署 of the Ministry of the Interior 內政部. For old building elevator safety inspection standards, please refer to Bureau of Standards, Metrology and Inspection (BSMI) CNS 2866 Elevators CNS 2866《昇降機》 safety general rules and urban renewal reconstruction and maintenance subsidy guidelines of various county and city governments 各縣市政府都市更新整建維護補助要點.
More old building renovation and structural seismic safety guides: Load-bearing wall and shear wall structure identification and demolition prevention regulation guide 承重牆與剪力牆結構辨識避免誤拆法規指南, and Post-earthquake building red tag and yellow tag seismic reinforcement evaluation guide 地震後房屋紅單黃單耐震補強評估指引.
6. Frequently Asked Questions FAQ
Q1: After adding an elevator, how much are the elevator's "public electricity fees" and "monthly regular maintenance fees"? Q1: 加裝電梯之後, 電梯的"公共電費"跟"每個月定期保養維護費"大約多少錢?
After the elevator is completed and put into use, it belongs to the common property of all funded residents. Monthly routine maintenance is carried out by qualified elevator maintenance manufacturers (such as Yungtay, Glartek, Mitsubishi, or sub-brands) 每個月由合格電梯維護廠商 (如永大, 崇友, 三菱或副牌) 進行定檢保養, and the fee is about NT$ 2,500 to NT$ 4,500 per month NT$ 2,500 至 NT$ 4,500 元/月; plus three-phase 220V/380V power electricity fees for independent electricity meters 獨立電表 (about NT$ 500 to NT$ 1,200 per month NT$ 500 至 NT$ 1,200 元/月), the average monthly operation and maintenance expenditure of the whole building is about NT$ 3,500 to NT$ 5,500 NT$ 3,500 至 NT$ 5,500 元, shared equally by each using household at a few hundred NT dollars per month 由使用各戶平均分攤每戶每月約數百元.
Q2: What should be done if, after adding an outdoor elevator tower and reaching the half-floor landing of the stairs, one still has to walk half a flight of stairs to enter home? Q2: 戶外加裝電梯塔, 抵達樓梯半樓平台後, 還是要走半層樓梯才能進家門怎麼辦?
This is the most common "half-floor riding pain point" encountered with outdoor elevators! If seniors in wheelchairs cannot walk those 7 to 8 steps at all 若長輩坐輪椅完全無法走那 7 至 8 階樓梯, professional architects will evaluate "Direct Access to Balcony (Balcony Entry Construction Method)" "直通陽台 (陽台進出工法) ": that is, the elevator tower entrance does not stop at the half-floor of the stairwell, but designs a long corridor to stop directly at "the height of each floor's own rear balcony or front balcony" 各樓層自家後陽台或前陽台高度. As long as the balcony parapet is cut and changed into an airtight security door 將陽台的女兒牆切開改為氣密防盜門, the senior's wheelchair can smoothly slide from the outdoor first floor directly into their own indoor home, achieving truly zero height difference "full barrier-free passage" 達到真正零高低差的"全無障礙通行".
Q3: If the first-floor residents resolutely disagree and refuse to sign, can construction really not proceed at all? Q3: 一樓住戶堅決不同意簽名, 工程真的完全動不了嗎?
If the urban renewal reconstruction and maintenance procedure or specific projects are followed according to regulations, the statutory consent ratio has been relaxed to 3/4 (75%) 3/4 (75%) . At the legal level, even if a few households disagree, there is still an administrative possibility of obtaining a construction license. However, at the realistic level, if the first floor launches fierce protests, blocks engineering vehicles from entering and exiting, or files servitude lawsuits, the construction period is often forced to be delayed for several years. Therefore, the wisest practice is: enthusiastic resident representatives negotiate from multiple sides, and high floors proactively promise to compensate the first floor with front-door beautification and repair, and exempt elevator fees entirely, resolving the deadlock through win-win mutual benefit 因此最智慧的作法是: 由熱心住戶代表多方協商, 由高樓層主動承諾補償一樓門前美化修繕, 全免電梯費用, 以雙贏互利化解僵局.
Q4: Will adding an elevator to an old apartment cause house tax to increase? Will it appreciate when the house is resold? Q4: 老舊公寓加裝電梯, 會導致房屋稅增加嗎?房屋轉手時會增值嗎?
After adding an elevator, the tax collection office will reassess the current value of the house according to the elevator construction cost and floors, and each household's annual house tax usually only increases by about several hundred to a little over a thousand NT dollars 房屋稅通常僅增加約數百元至千餘元, which is an extremely slight burden; however, in the real estate market, old apartments that originally climbed 4 floors or 5 floors and received little interest, once upgraded to "elevator mansions" "有電梯華廈", their market resale transaction unit price per ping can usually immediately surge by 15% to 30% or more 立即暴增 15% 至 30% 以上, and the total appreciation benefit far exceeds the hundreds of thousands of NT dollars of engineering costs initially shared 總增值利益遠遠超過當初分攤的數十萬元工程款!