Under the Statute for Expediting Reconstruction of Urban Dangerous and Old Buildings (《都市危險及老舊建築物加速重建條例》, known as the Dangerous and Old Buildings Act 危老條例), the early-bird "time-based FAR bonus" (時程獎勵) officially dropped to 0% on May 12, 2025 (民國 114 年 5 月 12 日); current reconstruction applications must rely on the "scale bonus" (規模獎勵, starting at a site area of 200 m²) combined with seismic, green building, smart building, and setback bonuses to reach the maximum 1.3x base floor area ratio (or 1.15x original building floor area ratio), and Article 5 of the current Act sets the application deadline at May 31, 2027 (民國 116 年 5 月 31 日). Because the Act imposes no minimum site area but requires 100% consent from all land and legal building owners within the project boundary, small sites under 200 m² face both reduced floor area bonuses and high unit construction costs now that the time bonus is zero. Based on statutory texts in the National Laws and Regulations Database verified on 2026-11-07, this article summarizes eligibility, FAR bonus formulas, tax breaks, and small-site alternatives.
3 core thresholds for dangerous-and-old reconstruction and the "May 31, 2027" application deadline
The Statute for Expediting Reconstruction of Urban Dangerous and Old Buildings moves faster than standard urban renewal because it bypasses lengthy urban renewal business plan and rights-transformation hearings, allowing the building authority to review a "reconstruction plan" (重建計畫) directly for a building permit. Qualifying for this track requires meeting the strict criteria of Articles 3 and 5:
- Applicable scope and building eligibility (Article 3): The property must sit within an "urban planning area" (都市計畫範圍內), be a legal building not designated by the competent authority as having historical, cultural, artistic, or commemorative value, and meet one of three conditions: (1) notified by the building authority under building or disaster-prevention laws for mandatory demolition within a deadline, immediate demolition, or mandatory retrofitting/demolition due to imminent danger; (2) failing to reach the minimum grade in a structural safety performance assessment; or (3) building age of 30 years or older whose structural safety performance assessment shows seismic capacity below the required standard, and where structural retrofitting is not cost-effective or the building lacks an elevator (昇降設備). Most 4- and 5-story walk-up apartments without elevators in Taipei and New Taipei qualify under Subparagraph 3 ("30+ years old + preliminary seismic assessment below standard + no elevator").
- Consent threshold (Article 5 paragraph 1): To draft a reconstruction plan, the applicant must obtain the consent of all (100%) land and legal building owners within the reconstruction plan boundary. Even 1 dissenting owner prevents that land parcel from being included (unless the dissenting parcel is excluded by redrawing the site boundary).
- Reconstruction plan application sunset deadline (Article 5 paragraph 2): The statute provides that "applications for the reconstruction plan in the preceding paragraph shall be implemented until May 31, 2027 (中華民國一百十六年五月三十一日)". Homeowners wishing to apply under the current Act must complete their preliminary seismic assessment, secure 100% consent, and file the reconstruction plan with the municipal or county/city government by that statutory date (subject to any subsequent legislative amendments).
To check whether your building's occupancy permit issue date has passed the 30-year mark, read the site's guide to checking building age via occupancy permit dates and building transcripts and calculate it with the building age calculator.
How to reach the FAR cap after the time bonus hit zero: Article 6 and the FAR Bonus Regulations
Under Article 6 paragraph 1 of the Dangerous and Old Buildings Act, post-reconstruction building floor area may not exceed "1.3 times the base floor area ratio (a maximum 30% bonus)" or "1.15 times the original building floor area ratio (a maximum 15% bonus over original floor area)". During the first 8 years of the Act, filing early earned a "time bonus" stepping down from 10% to 1%, plus up to 10% combined with the "scale bonus" (for an overall cap of 40%).
However, starting May 12, 2025 (民國 114 年 5 月 12 日), the "time bonus" officially dropped to 0%. New applications must now rely entirely on physical performance items and the "scale bonus" under the Regulations on Building Bulk Bonus for Urban Dangerous and Old Buildings (《都市危險及老舊建築物建築容積獎勵辦法》):
| FAR bonus category | Bonus range (per the FAR Bonus Regulations) | Eligibility criteria and site-area requirements |
|---|---|---|
| 1. Original building floor area above base FAR or structural safety assessment bonus (Articles 3 and 4) | 2% to 10% | Where original building floor area exceeds base FAR, or by danger tier under Article 3 paragraph 1 of the Act (Subparagraph 1: 10%, Subparagraph 2: 8%, Subparagraph 3: 6%) |
| 2. Site setback bonus (Article 5) | 8% or 10% | 10% for setting back at least 4 meters clear from planned roads and neighboring property lines with an unroofed pedestrian walkway; 8% for a 2-meter clear setback (narrow small sites often cannot fit a building footprint and ramp after setting back) |
| 3. Seismic design bonus (Article 6) | 2% to 10% | 10% for obtaining the Seismic Design Label (耐震設計標章), or 2% to 6% for passing structural safety performance assessment grades |
| 4. Green building, smart building, barrier-free environment, and public facility land dedication (Articles 7 to 10) | About 2% to 10% per item | Awarded by grade for Green Building Label (2% to 10%), Smart Building Label (2% to 10%), barrier-free housing design (3% to 5%), and public facility land dedication (up to 5%); certain higher label tiers require a site area of over 500 m² and a refundable performance bond agreement |
| 5. Time bonus (Article 12) | 0% (reduced to zero from May 12, 2025 / 114 年 5 月 12 日) | No time-based FAR bonus is granted from Year 9 of implementation onward |
| 6. Scale bonus (Act Article 6, Regulations Article 11-1) | 2% to 10% | Where the dangerous/old building site plus merged neighboring land reaches 200 m² (about 60.5 ping), 2% of base FAR is granted; for every additional 100 m² (about 30.25 ping), an extra 0.5% of base FAR is granted (capped at 10% of base FAR) |
Here is how the "scale bonus" arithmetic works: if your site area is only 150 m² (about 45 ping), it falls short of the 200 m² threshold, so with the time bonus at zero your time/scale bonus is 0%; if you merge two neighboring walk-up apartments to reach a 600 m² site (about 181.5 ping), the scale bonus becomes 2% + [(600 - 200) ÷ 100] × 0.5% = 4%; reaching the full 10% scale bonus cap requires a combined site area of 1,800 m² (about 544.5 ping).