Taiwan Pre-Sale Home Contract Review and Escrow Guide
🇹🇼 Looking for the Chinese version of this article?切換至繁體中文版 →

Taiwan Pre-Sale Home Contract Review and Escrow Guide

This article is general information for reference only and is not legal, tax, medical or engineering advice. Rules, fees and subsidies change; check the latest notice from the responsible authority before acting. For electrical, gas, structural or health risks, consult a licensed professional.

This is the English edition of a Chinese article, adapted with AI assistance and checked against the original. Where the two differ, the Chinese version and the official sources it cites prevail.

Purchasing pre-sale homes in Taiwan is strictly protected by the Mandatory and Prohibitory Terms of Standard Form Contracts for Pre-Sale Home Sales issued by the Ministry of the Interior and the Equalization of Land Rights Act (平均地權條例). Buyers enjoy 5 fundamental statutory rights: at least 5 days of contract review prior to signing; mandatory developer provision of 1 of 5 escrow trust mechanisms; unconditional 100% price compensation for floor area shortages (with cancellation rights if discrepancies exceed 3%); a statutory 5% handover retention payment that cannot be cut to NT$50,000; and a strict ban on contract resales taking effect July 1, 2023 (112 年 7 月 1 日).

Important Reminder: If developers or sales agents demand buyers pay earnest money before inspecting contracts, or require checking clauses claiming voluntary waiver of the 5-day review period, such waivers are legally invalid under the Consumer Protection Act and can be reported to municipal land bureaus for administrative fines.

Core Priority 1: At Least 5-Day Review and Red Slip Transfer Ban

From placing earnest deposits (commonly called red slips or small deposits) to signing formal contracts, buyers must know two statutory red lines:

  • Statutory Contract Review Period of at Least 5 Days: Developers must provide complete pre-sale sales contracts (including land fractions, common area allocations, equipment schedules, and floor plans) for buyers to review at home for at least 5 days. If buyers decide not to purchase during this period, developers must refund deposits unconditionally in full.
  • Red Slips Must Not Disadvantage Buyers and Cannot Be Transferred: Under Article 47-3 of the Equalization of Land Rights Act, written receipts issued upon receiving deposits cannot reserve sales rights or disadvantage buyers, and holders cannot resell or transfer red slips to third parties. Violators face municipal fines between NT$150,000 and NT$1,000,000 (15 萬至 100 萬元).

Core Priority 2: Comparing 5 Escrow Performance Guarantee Mechanisms

Pre-sale construction typically spans 3 to 5 years; if developers encounter liquidity crunches or project abandonment, whether buyers recover deposits depends entirely on which of the 5 statutory escrow mechanisms applies:

Escrow Mechanism NameOperational Principle and Account Custody RulesBuyer Protection Level If Developer Fails
1. Price Refund Guarantee (價金返還之保證)Guaranteed by financial institutions; buyer payments are deposited into escrow and cannot be accessed by developers until completion and handover.Highest (Safest): If developers fail to complete construction on schedule, financial institutions refund 100% of paid principal and interest. Rare in practice due to heavy capital constraints on builders.
2. Real Estate Development Trust (不動產開發信託)Developers transfer project funds, buyer payments, and land titles to bank trusts, disbursing funds exclusively for construction milestones.Medium-High (Most Common): Funds are ring-fenced for engineering; however, money already disbursed to general contractors cannot be refunded, leaving buyers with remaining account balances.
3. Price Trust (價金信託)Buyer payments are placed into bank trust accounts and drawn down by builders according to verified construction progress.Medium (Most Common): Prevents absconding with down payments, but if projects stall mid-way, only unspent account balances remain; does not guarantee full principal refunds!
4. Joint Industry Peer Guarantee (同業連帶擔保)Another developer of equivalent capital, qualification tier, and clean credit history provides joint and several liability guarantees.Dependent on Guarantor: Buyers can demand the guaranteeing builder complete construction and handover unconditionally, but cannot demand cash refunds.
5. Association Joint Guarantee Agreement (公會辦理連帶保證協定)Established by national or municipal real estate development associations across member firms.Dependent on Association: Buyers can petition participating member builders to step in and complete construction and handover.

Note: When remitting signing deposits or milestone payments under trust arrangements, account names must explicitly read Bank Escrow Account rather than private developer accounts.

Core Priority 3: Discrepancies, 5% Retention Funds, and Resale Limits

Standardized pre-sale contracts impose statutory protections regarding cadastral survey discrepancies, handover retentions, and warranty terms:

Mandatory Contract TermMOI Statutory Standard (Mandatory Clause)Unlawful Contract Pitfalls (Invalid Terms)
Area Shortage (Registered Area < Contract Area)Any discrepancy where registered land or building area falls short must be fully compensated (100% price refund) with zero exemption thresholds!Unlawful clauses stating no compensation for errors within 1% or 2% are legally void; even 0.1 ping shortages must be refunded.
Area Excess (Registered Area > Contract Area)Buyers only compensate developers for excess area up to a maximum cap of 2% (buyers pay nothing for excess exceeding 2%).Unlawfully demanding buyers pay full prices for all excess floor areas.
Area Discrepancy Exceeding 3% Cancellation RightRegardless of whether area is short or excessive, if discrepancies reach 3% or greater, buyers may cancel contracts.Unlawfully raising cancellation thresholds to 5% or restricting rights exclusively to main interior spaces.
Handover Retention Fund (5% Final Balance)Self-funded payments must retain 5% of total property purchase price as handover retention, payable only after defect remediation.On a NT$20,000,000 property, statutory retention is NT$1,000,000; rogue builders illegally cut this to NT$50,000 via individual negotiated terms.
Statutory Warranty PeriodCalculated from handover date: 15 years for structural components and 1 year for fixed building fixtures and equipment.Unlawfully calculating warranties from use permit issuance dates, which precede handovers by months.

When attending initial defect inspections, bring our home inspection checklist tool to examine plumbing and tiles; closing taxes and notary charges are detailed in our home purchase taxes and deed tax guide. Under law, builders must register sales prices within 30 days of signing; explore our actual price registration lookup guide.

Pre-Sale Contract Assignment and Resale Restrictions (Equalization of Land Rights Act Art. 47-4):

Effective July 1, 2023 (民國 112 年 7 月 1 日), pre-sale buyers are strictly prohibited from assigning or reselling purchase contracts to third parties, and developers cannot facilitate transfers. Violators face fines between NT$500,000 and NT$3,000,000 (50 萬至 300 萬元). Only 3 statutory exceptions allow legal assignment:

  1. Transfers Between Spouses, Direct Line Relatives, or Second-Degree Collateral Relatives: Transfers to spouses, parents, children, grandparents, or siblings do not require prior government approval and can be executed directly with builders.
  2. Buyer Death Post-Signing: Processing statutory inheritance registrations.
  3. Major Life Hardships Approved by MOI Across 6 Categories: Including (1) involuntary unemployment exceeding 6 months; (2) severe illness or disability requiring over 6 months full-time care; (3) natural disaster property destruction requiring renting; (4) accidents resulting in third-party severe injury or death liabilities; (5) transfers among remaining co-buyers after one buyer passes away; (6) corporate mergers or dissolutions. Applications require municipal approval (limited to 1 unit nationwide per 2 years).

Frequently Asked Questions

Can Sales Centers Demand NT$100,000 Deposits Before Letting Buyers Review Contracts?

No. Fair Trade Commission precedents establish that sales centers must provide contract templates freely; demanding NT$100,000 deposits prior to home review is unlawful and subject to administrative penalties.

Does Price Trust Guarantee Full Down Payment Refunds If Developers Go Bankrupt?

No. Price Trust and Real Estate Development Trust only ring-fence funds for project milestones; if projects stall, buyers receive only unspent account balances rather than 100% refunds.

What Precautions Apply to Client Change (Customer Alteration) Requests?

Builders permit altering finishes before floors reach structural milestones; however: (1) material deductions refund wholesale costs without labor; (2) wet areas and plumbing stacks cannot be relocated; (3) signed alteration drawings cannot be modified further.

Can Buyers Claim Liquidated Damages If Developers Delay Property Handovers?

Yes. Under Clause 12 of MOI standard terms, unexcused delays incur daily interest of 0.05% (5/10,000) of paid property funds; delays exceeding 3 months entitle buyers to cancel contracts, recover all payments, and claim damages not less than 15% of total purchase price.

Last updated: 2026-11-01.