A water pipe pressure test closes off the indoor water supply piping, pressurizes it to a specified pressure and holds it for a specified time while you watch whether the gauge drops. The pass standard depends on the water authority's rules for water-use equipment and on the contract, and on site you should photograph the gauge reading and time at the start and at the end. This article covers indoor supply pipes (cold and hot water) only. For the water-fill test on drain pipes, see bathroom and kitchen leak and drainage inspection. The article does not give a fixed “how many kg, how many hours” because the numbers must follow the current provisions and the contract.
Water Pipe Pressure Test: Gauge, Hold Time, Pressure Drop

This article is compiled from publicly available online sources for general reference only; readers should independently verify and judge its accuracy, and it is not legal, tax, medical or engineering advice. Rules, fees and subsidies change; check the latest notice from the responsible authority before acting. For electrical, gas, structural or health risks, consult a qualified professional.
This is the English edition of a Chinese article, adapted with AI assistance and checked against the original. Where the two differ, the Chinese version and the official sources it cites prevail.
When a pressure test is needed
Acceptance before new piping is closed in
After new piping or re-piping is finished, test it before cement fill, tiling or board covering. A leak found after the wall is closed means breaking it open and redoing the work, at a cost far higher than testing in advance. So the contract should state that “a pressure test must be done before closing the wall and confirmed with the owner present,” rather than leaving it until the end. For the trade-offs between exposed and concealed pipes, see cost, pros and cons of exposed vs concealed water pipes in Taipei.
Confirming a suspected concealed-pipe leak
If the water bill suddenly rises or walls and floors are damp for no reason, first follow the water meter test for abnormal water bills to see whether the meter still runs after all water use is shut off. Once a leak is confirmed, use a pressure test to judge whether it is in this section of indoor supply pipe. A pressure test can only answer “does this pipe section leak”; it cannot point directly to where the leak is, and locating it relies on the sectional tests below or other inspection methods.
Test cold and hot water pipes separately
Cold and hot water pipes differ in pipe material, fittings and operating temperature, so pressurize and record them separately. Whether appliances such as water heaters and mixer taps are included in the pressurized range should be confirmed with the technician beforehand, so the pressure does not exceed the pressure rating marked on the appliance.
Pressure test steps
Before testing, prepare the pressure gauge, a test pump, plugs or blind plates for sealing, and a phone for photos. The following is the general procedure; the actual pressure, time and medium still follow the provisions, the contract and the pipe manufacturer's installation manual.
- Confirm the test range and the marked pressure rating of the pipes and fittings.
- Close the inlet valve and isolate the pipe section to be tested.
- Seal all outlets.
- After bleeding the air from the pipes, pressurize slowly to the specified pressure.
- Record the starting pressure and time, hold for the specified time, then record the ending pressure.
- Release the pressure, remove the seals and restore the fixtures.
Closing and sealing the outlets
Close the main inlet valve first, then isolate both ends of the section to be tested. Seal the outlets with plugs, blind plates or end caps, and handle fixture ends such as taps and toilet angle valves according to the state of the work. The sealed points are themselves common leak points, so record the sealing method on the test range diagram to avoid mistaking them for pipe leaks.
Bleeding air and pressurizing
Bleed air from the outlet at the highest point of the piping, and seal it only when the water coming out no longer carries bubbles. Pressurize slowly with the test pump. The gauge range must cover the test pressure; stop once the specified value is reached, and never exceed the marked pressure rating of the pipes and fittings. Whether to pressurize with water or another medium follows the pipe manufacturer's installation manual and the provisions.
Holding pressure and observing
After pressurizing, note the starting pressure and time. During the hold, check the joints, walls and floor for seepage and record the ambient temperature. Do not end early just because nothing changes in the first few minutes; read the gauge again when the time is up, since only the comparison of the two numbers is meaningful.
Releasing pressure and restoring
Release the pressure slowly with the relief valve; do not open a seal directly to dump the water quickly. After removing the seals and restoring taps and fixtures, reopen the inlet valve and check each joint for seepage again, and if needed confirm with the water meter test.
How to find the pressure and time standards
Regulations and water utility rules
For the test pressure and hold time, check the current provisions of the 《自來水用戶用水設備標準》 in the National Laws and Regulations Database. If the home is in the supply area of 臺北自來水事業處 or 臺灣自來水公司, internal-pipe review and inspection have separate procedures, so confirm with the water supplier or the contractor before work starts. Provisions get amended, so write the date of your lookup and the article number into the acceptance record, and do not reuse word-of-mouth numbers such as “10 kg for 1 hour.”
The contract can be stricter than the rules
The contract can specify the pressure value, the hold time and the allowed pressure drop, and can set conditions stricter than the rules, but it still must not exceed the marked pressure rating of the pipes and fittings. It is advisable to word the contract as “follow the current provisions and the pipe manufacturer's manual, take the stricter, and do not exceed the marked pressure rating,” with both sides confirming it before the test, to avoid arguments over the numbers afterwards.
How to read a pressure drop
Slow drop versus fast drop
A fast drop in a short time is mostly a seal that came off, a joint that came loose or a damaged pipe body, so stop immediately and release the pressure. A slow drop may come from a small leak, residual air or temperature change; rule those out, retest once, and only then draw a conclusion.
Effects of temperature change and joint leaks
Water in the pipe expands when heated and contracts when cooled, so the pressure reading shifts slightly with it, more so on hot water pipes and pipes in direct sun. Leaks at the gauge fitting, the pump fitting and the sealing plugs can also cause a false drop, so check the test equipment itself before retesting.
Finding the leaking section by sectional testing
Add valves or end caps at branch points to divide the piping into several sections and pressurize each separately. Subdivide the section that drops until it is narrowed to a range you can deal with, and only then decide where to open the wall or reroute the pipe.
The table below sets out how the owner and the technician divide the work during a pressure test.
| Item | Owner can confirm on site | Needs the plumber/electrician |
|---|---|---|
| Test range and seal locations | Check against the test range diagram | Actual isolation and sealing |
| Pressurizing | Watch the gauge as pressure rises | Operate the pump and control the pressure |
| Reading the gauge and photos | Confirm the start and end numbers and times | Provide the equipment and the readings |
| Releasing pressure and removal | Confirm fixtures are restored | Release pressure slowly and remove the seals |
| Judging the cause of a drop | Listen to the explanation and keep records | Rule out equipment factors and test by section |
Records the owner should keep at acceptance
Start and end gauge photos with times
Take one photo at the start and one at the end. Each photo should show the numbers on the dial, the needle position, and the phone time or a clock in the same frame. Use the same gauge before and after to avoid error from swapping gauges.
Test range diagram
A hand-drawn sketch is enough, marking the pipe section tested, the seal locations and the gauge location. At acceptance you can also check item by item against the home inspection checklist.
Signatures of those present
The owner, the technician and the person in charge on site sign the record sheet and note the date, so there is evidence if a warranty or liability dispute comes up later. For related risks, see renovation risk control. The record sheet columns can follow the table below.
| Date | Pipe section | Starting pressure | Ending pressure | Hold time | Result |
|---|---|---|---|---|---|
| (fill in) | Cold water pipe / hot water pipe / section number | (gauge value from photo) | (gauge value from photo) | (start and end times) | Pass / fail / retest |
FAQ
How many kg of pressure and how long should a water pipe test run?
This article does not give fixed numbers. Check the current provisions of the 《自來水用戶用水設備標準》, the water supplier's rules and the contract, confirm the pressure does not exceed the pipe's rated pressure, and write the article number you relied on into the record.
Is a slight pressure drop normal?
Whether it is acceptable depends on whether the provisions and contract state a tolerance. Without an agreed value, do not treat it as normal on your own; first rule out temperature, residual air and leaks in the test equipment, then retest to confirm.
Could pressure testing damage old water pipes?
There is a risk. The pipe walls, joints and welds of old piping may have reduced pressure capacity, and pressurizing can make a spot that was barely holding burst. Before testing, have the technician assess the condition of the pipes, and confirm the pressure and whether to test in sections before deciding whether to test at all.
Can I do a pressure test myself?
The owner can be present to confirm, take photos and keep records, but pressurizing and sealing are best left to the technician. Excessive pressure can make joints pop out or the pipe body burst, causing injury and water damage.
Sources
- National Laws and Regulations Database (全國法規資料庫): 自來水用戶用水設備標準 (verified 2026-11-11): the test pressure and hold time follow the current provisions
- 臺北自來水事業處: rules on inspection of internal water-use piping (verified 2026-11-11): inspection procedures for the 北水 supply area
- 臺灣自來水公司: procedures for review and inspection of internal water-use piping (verified 2026-11-11): review and inspection procedures for the 台水 supply area