Taiwan Restaurant Fit-Out: Three-Phase Power, Grease Traps

Taiwan Restaurant Fit-Out: Three-Phase Power, Grease Traps

This article is compiled from publicly available online sources for general reference only; readers should independently verify and judge its accuracy, and it is not legal, tax, medical or engineering advice. Rules, fees and subsidies change; check the latest notice from the responsible authority before acting. For electrical, gas, structural or health risks, consult a qualified professional.

This is the English edition of a Chinese article, adapted with AI assistance and checked against the original. Where the two differ, the Chinese version and the official sources it cites prevail.

When renting a street-front shop to open a restaurant, specialty cafe, brunch place or bakery, one of the most common causes of a badly overrun fit-out budget, or even a delayed opening day, is not carefully checking the shop's “power phase and contract capacity” and its “kitchen drainage grease-handling conditions” before signing the lease agreement. A shop that used to be a clothing store, clinic or office usually has original wiring that serves only lighting and ordinary sockets. Once food-service equipment (such as a dual-outlet commercial espresso machine, a commercial convection oven, a high-temperature dishwasher, a large upright freezer and a floor-standing air conditioner) arrives together, either of two things can badly lengthen the preparation period and the construction spend: the total load exceeds what the original single-phase electricity meter can carry, or kitchen wash drainage has no grease trap installed as required, so grease hardens and blocks the drain pipe and the operator is fined by the environmental and building authorities. In addition, before renting a ground-floor shop in a residential zone for a food business, also confirm the land-use zoning, the use stated on the building's occupancy permit (for example whether a change to a G-3 eatery or B-3 dining venue is involved), and the rules on cooking fume and odor emissions.

1. Shop Power Assessment: When Do You Need to Apply to Taipower for a Single-Phase to Three-Phase Change?

A typical residential-type ground-floor shop is usually wired as “single-phase three-wire (110V / 220V)”. Taiwan's current rules do not rigidly state that exceeding a certain number of kW forces a change to three-phase. Whether you need to apply to Taipower for three-phase supply (commonly three-phase three-wire 220V or three-phase four-wire 220V/380V) depends mainly on three objective conditions: first, whether the commercial kitchen equipment specifies three-phase motors or three-phase heaters (for example a large commercial oven, ice machine or central air-conditioning unit); second, the maximum load capacity when all equipment in the shop runs at the same time; third, the supply conditions of the local Taipower distribution line (transformer). In practice, when the combined power of high-power electric heating equipment and air conditioning in the shop approaches or exceeds 15 kW ~ 20 kW, it is strongly recommended that, before signing the formal lease, you commission a qualified electrical contractor to bring the equipment specification sheet to the site for assessment.

Application and construction stage Handling party and qualification requirements 2026 cost structure and indicative range (NT$) Notes for lease signing and future move-out negotiation
Taipower line installation fee (external line expansion fee) Taiwan Power Company (Taipower), charged according to the added contract capacity applied for Charged by the added capacity (kW / horsepower) and the distance Taipower must run the external line; indicative approx. NT$12,000 - NT$45,000+ This is a statutory fee with a receipt paid to Taipower, and ownership of the external equipment belongs to Taipower (it cannot be removed at move-out and no refund can be requested from Taipower); because adding power improves the shop's hardware, it is advisable before signing to negotiate with the landlord on sharing the cost or offsetting it against a rent-free fit-out period
Design drawings, electrical equipment inspection and submission for review Handled by an electrical contractor with the appropriate grade of qualification together with a professional electrical engineer, depending on project size and regulations Indicative approx. NT$15,000 - NT$30,000 The application process includes design drawing review, Taipower external line work, completion inspection of the internal wiring, and electricity meter installation; the full process usually takes 3 to 6 weeks, so it must be built into the overall fit-out schedule
Meter box replacement and main distribution panel work after the meter Carried out by a qualified electrical contractor Depends on the length of the feeder after the meter, wire gauge and number of circuits; indicative approx. NT$35,000 - NT$85,000 If the landlord requires the electricity meter to be restored to the original single-phase specification at move-out, a separate alteration and removal fee must be paid; it is advisable to state in black and white in a special clause of the lease agreement “three-phase power equipment is kept at move-out; no need to change back to single-phase”

2. Legal Basis and Engineering Selection: Grease Trap (Grease Interceptor) Requirements for Restaurant Kitchens

Many first-time restaurateurs, to save money when fitting out the kitchen, simply place a plastic strainer under the dish sink. Less than three months after opening, the entire kitchen drain pipe is completely blocked by solidified animal and vegetable grease, and it can even trigger compensation disputes over sewage backing up into the lower floors of the whole building.

Under Article 29, Paragraph 1, Subparagraph 1 of the current Building Technical Regulations (建築技術規則), Building Equipment Part, it is expressly provided: “For buildings such as restaurants, shops, eateries, markets, shopping centers, hotels, factories, government offices, schools, hospitals, elderly welfare institutions, welfare institutions for persons with disabilities, placement and care institutions for children and youth, and clubs, the sink and container drainage of attached food cooking or preparation areas shall be fitted with a grease interceptor.”

Multi-layer regulatory compliance reminder: Restaurant owners must understand that Article 29 of the Building Technical Regulations only sets the principle that a grease interceptor “must be installed”. The grease trap's effective volume calculation, retention time, construction details and waste-oil removal are also bound by the Ministry of the Interior's Technical Specifications for Design of Building Water Supply and Drainage Equipment, each county and city's sewer management bylaws, and the Ministry of Environment's Water Pollution Control Act and Waste Disposal Act (a small box bought online and dropped in does not casually meet inspection standards):

  1. Effective volume calculation and material selection (per the Technical Specifications for Design of Building Water Supply and Drainage Equipment): The effective volume of a grease trap should be calculated from the total water volume of the kitchen wash sinks, peak drainage flow and the number of diners seated in the shop, ensuring greasy wastewater stays in the tank long enough (usually required to be 2 to 3 minutes or more) for the grease to cool, float up and separate from the water. Common materials are SUS304 stainless steel (pay attention to plate thickness and rust-proofing at welds) or corrosion-resistant FRP fiberglass; the internal baffle construction is chosen according to the product design and the engineering drawings. The installation position must also keep working space above to open the lid and skim the grease; it must not be sealed in by fixed kitchen equipment.
  2. Pipe slope and cleanout (Cleanout) design: The drain pipe from the wash sink to the grease trap should keep a smooth fall (a commonly designed slope is 1/50 to 1/100). At bends in the piping, 45° elbows or large-radius elbows are preferable (avoid sharp 90° right-angle elbows, which let grease build up), and cleanouts should be reserved at key turning points to make regular drain-clearing maintenance easier later.
  3. Daily skimming and lawful waste cooking-oil removal records (guarding against penalties under the Water Pollution Control Act and sewer inspections): Food scraps and the floating oil layer caught in the grease trap are strictly prohibited from being scraped or flushed with hot water into the public sewer (hot water can melt grease temporarily, but once it flows to the cooled downstream public piping it will immediately solidify into lumps). Shops should skim the grease sludge regularly according to how oily their operation is (after closing each day or weekly) and hand it to a qualified waste cooking-oil recycler or waste removal organization approved by the Ministry of Environment, and properly keep the removal manifests for inspection by the environmental protection bureau and the water resources sewer authority (where a grease trap is not installed as required or not cleaned regularly and grease discharged into the public sewer causes a blockage, the competent authority may, in accordance with the law, order improvement within a time limit and impose a fine).

3. Business Electricity Cost Estimates: When Does It Make Sense to Switch from Non-Time-of-Use to Time-of-Use Rates?

Many restaurant owners, on receiving their first high summer-month (months 6 to 9, June to September) electricity bill, rush to apply to Taipower to switch to “time-of-use rates”. But owners must note: once a time-of-use plan is chosen and the change succeeds, under Taipower's business rules you must generally wait a full 1 year before you can apply to change again, and the billing structure and over-contract handling rules also differ by customer category (such as “residential and commercial simple time-of-use rate” versus “low-voltage power / standard time-of-use rate”). (For low-voltage power customers with a stated “contract capacity (kW)”, a fixed “basic charge” must be paid every month according to the contract capacity, and when the actual maximum demand exceeds the contract capacity, under Taipower's business rules the excess portion is charged an over-contract surcharge at 2 to 3 times by tier; if the estimate is off, the over-contract penalty often eats up the electricity cost you originally saved.)

According to the structure of the current tariff schedule of Taiwan Power Company (Taipower) (the following uses the lighting business rate and the current simple three-period time-of-use unit prices as an indicative baseline; for the actual latest rates and period divisions, check the tariff schedule currently announced by Taipower):

  • Lighting business rate (non-time-of-use / progressive billing): Billed progressively in tiers by total monthly consumption (up to 330 kWh, 331–700, 701–1,500, 1,501–3,000, and 3,001 kWh and above); in summer months (6/1–9/30), the top tier above 3,000 kWh has the highest unit price (over NT$6 per kWh). The advantage is that there is no contract capacity limit and no over-contract penalty.
  • Current “residential and commercial simple time-of-use rate (three-period)” reference unit prices (Taipower's current announced baseline for 2026): The energy charge has no usage tiers and is billed by time period instead. In summer months (6/1–9/30), the weekday peak period (16:00–22:00) energy charge is NT$7.13 per kWh, the semi-peak period (09:00–16:00 and 22:00–24:00) is NT$4.69 per kWh, and the off-peak period (00:00–09:00 and the whole day on Saturday and Sunday off-peak days) is NT$2.06 per kWh, plus a monthly basic charge (if you choose the standard low-voltage time-of-use rate or a contract-capacity plan, the basic charge is calculated separately according to the applied contract capacity in kW).

Decision formula for restaurant owners:

  • Cases where blindly switching to the three-period time-of-use rate is not recommended: If your restaurant is a dinner-type izakaya, hot pot restaurant or yakiniku restaurant, with the main business hours and full air-conditioning load concentrated from 17:00 to 22:00 (which falls exactly in the summer-month peak period of NT$7.13 per kWh under the three-period rate) and almost no electricity demand during the daytime off-peak period, rashly switching to the three-period time-of-use rate may instead make the electricity bill rise rather than fall!
  • Cases worth evaluating for a time-of-use rate: Conversely, if the shop has a large walk-in freezer running 24 hours a day, multiple ice machines or baking proofers, or its main business hours are concentrated in the daytime (for example a brunch place or daytime cafe that avoids the 16:00–22:00 peak period), and monthly total consumption stays above 3,000 ~ 4,000 kWh, it is recommended to first download past load curves by time period through the Taipower app or the customer service system for an accurate estimate, confirm that the energy charge saved is greater than the basic charge expense, and carefully assess the contract capacity ceiling before submitting the change application.